Capital Projects
Annual construction projects are identified through a 10-year forecast process. The capital projects schedule below identifies current or proposed projects and estimated timelines for commencing projects.
Capital Projects Scheduled for 2024
The planned Public Works capital projects for 2024 are outlined below:
County Road 3 Glamorgan Road – Crack Sealing (County Road 503 to a point 3,250 metres north) |
Start date tbd Duration Approximately 1 to 2 days Obey Crews Directions Expect delays |
County Road 3 Glamorgan Road – Crack Sealing (Highway #118 to a point 3700 metres south) |
Start date tbd Duration Approximately 1 to 2 days Obey Crews Directions Expect delays |
County Road 3 Glamorgan Road - Asphalt Rejuvenator Application (Highway #118 to a point 3700 metres south) |
Start date tbd Duration Approximately 2 to 5 days Obey Crews Directions Expect delays, slippery and dusty conditions |
County Road 7 Kennisis Lake Road– Asphalt Rejuvenator Application (West Guilford Bridge to a point 700 metres north) |
Start Date tbd Duration Approximately 2 to 5 days Obey Crews Directions Expect delays, slippery and dusty conditions |
County Road 8 Kawagama Lake Road – Asphalt Rejuvenation Application (Highway #35 to County Road 12 – 800 metres) |
Start Date tbd Duration Approximately 2 to 5 days Obey Crews Directions Expect delays, slippery and dusty conditions |
County Road 10 Elephant Lake Road – Double Surface Treatment -(County Road 648 to a point 3055 metres north) |
Start Date: June 21st 2024 Duration 4 to 8 weeks Obey Crews Directions Surface Treatment is Completed, Pavement Markings still need to be completed. |
County Road 10 Elephant Lake Road – Single Surface Treatment – (Kingscote Lake Road to a point 1610 metres south) |
Start date: June 19th 2024 Duration 2 to 4 weeks Obey Crews Directions Surface Treatment is Completed, Pavement Markings still need to be completed. |
County Road 18 Kashawigamog Lake Road – Crack Sealing (County Road 21 to County Road 17 1440 metres) |
Start date tbd Duration 1 to 2 days Obey Crews Directions Expect delays |
County Road 19 Harburn Road – Double Surface Treatment (Tattersal Road to a point 4,350 metres east) |
Start Date: June 17th 2024 Duration 4 to 8 weeks Obey Crews Directions Surface Treatment is Completed, Pavement Markings still need to be completed. |
County Road 19 Harburn Road – Single Surface Treatment – (Hodgson Road to Haliburton Lake Road 815 metres) |
Start Date: June 17th 2024 Duration 4 to 8 weeks Obey Crews Directions Surface Treatment is Completed, Pavement Markings still need to be completed. |
County Road 503 - Hot Mix Rehabilitation (Kinmount to Furnace Falls Bridge – 6,870 metres) |
Start Date tbd Duration 8 to 12 weeks Obey Crews Direction Expect delays, loose top surface, dusty conditions |
County Road 648 Loop Road - Crack Sealing (Harcourt to a point 3000 metres east) |
Start date tbd Duration Approximately 1 to 2 days Obey Crews Directions Expect delays |
All County Roads – Pavement Markings/Line Painting |
Start date: July 8th 2024 Duration Approximately 6 to 8 weeks “Stay Back” from Painting Equipment “Do Not Pass” unless directed by Crew Obey Crews Directions |
Please note that schedules are subject to change.